New Resource Planning.
Transmission Planning, current year- future(s).
Capacity Planning.
Keywords: LMR, Load Modifying Resource, Behind the Meter, Demand Resource, Resource Adequacy, Planning, Module E, Module E-1
emand Response (DR) Testing Requirements
1004 view(s)
Jan 10, 2025
Keywords: XEFORd, GADS, Generator Data, Resource Adequacy, Planning, Forced Outage,
Defines and describes XEFORd (Equivalent Forced Outage Rate Demand)
522 view(s)
Jan 10, 2025
Keywords: ZRC, Zonal Resource Credit, Resource Adequacy, Transfer, Exchange, Resource Adequacy
Zonal Resource Credit (ZRC) transactions allow two Market Participants to exchange Zonal Resource Credits (ZRCs).
1836 view(s)
Dec 4, 2024
Keywords: Fixed Resource Adequacy, Plan, Planning, FRAP, Resource Adequacy, Planning Reserve Margin, Local Clearing, Local Resource, Submit
Describes the Fixed Resource Adequacy Plan requirements.
1588 view(s)
Jan 10, 2025
Keywords: Fixed Resource, FRAP, Zonal Resource Credit, ZRC, Resource Adequacy, Planning, Reserve Margin, Local Clearing, Local Resource
Describes the Fixed Resource Adequacy Plan
1192 view(s)
Jan 10, 2025
Keywords: GADS, Generator Availability Data, Import, PowerGADS, Resource Adequacy, Planning
Types of data imported to MISO PowerGads system.
248 view(s)
Jan 10, 2025
Keywords: GADS, Generator Availability, Add, PowerGADS, GVTC, Capacity, Resource Adequacy, Planning
Generation Resources greater than or equal to 10 MW (based on Generation Verification Tested Capacity (GVTC)) must submit their Generator Availability Data
91 view(s)
Feb 6, 2025
Keywords: GADS, Generator Availability, Reporting, Timeline, Resource Adequacy, Planning
GADS data must be submitted on a quarterly basis.
176 view(s)
Jan 10, 2025
Keywords: GADS, Generator Availability Data, PowerGADS, Unlock, Resource Adequacy, Planning, Capacity
PowerGADS data entry is locked after the submission deadline has passed.
520 view(s)
Feb 6, 2025
Keywords: GVTC, Generator Verification Test, Correction, Resource Adequacy, Planning
Corrections for Air Temperature, Relative Humidity and Cooling Water Temperature are applied based on unit type.
964 view(s)
Dec 4, 2024
Keywords: GVTC, Generator, Verification, Test, Capacity, Resource Adequacy, Planning, Summer, Peak, Planning
Brief description of GVTC value and location of summer peak date and time.
1574 view(s)
Jul 1, 2024
Keywords: PRMR, Calculated, Calculation, Planning Reserve Margin, Local Resource Zone, Planning, Resource Adequacy
Planning Resources are maintained for each Local Resource Zone (LRZ) to meet the MISO footprint’s Planning Reserve Margin Requirement (PRMR).
831 view(s)
Jul 1, 2024
Keywords: ICAP, Defer, Deferral, Credit Requirement, Resource Adequacy, Planning, Auction, Request
MISO will adjust the Market Participant’s credit requirements within ten (10) Business Days of the full ICAP being met and validated by MISO.
458 view(s)
Jul 1, 2024
Keywords: ICAP, Installed Capacity, Defer, Deferral, Planning Resource Auction, Zonal Resource Credit, Resource Adequacy
ICAP Deferrals allow Market Participants (MPs) to participate in the Planning Resource Auction (PRA) using Zonal Resource Credits (ZRCs) that meet defined
731 view(s)
Jul 1, 2024
Keywords: LCR, Local Clearing, Local Resource Zone, LRZ, Resource Adequacy, Planning
MISO will determine the import and export limits for each Local Resource Zone (LRZ) by performing a transfer analysis study.
1491 view(s)
Jun 3, 2024
Keywords: LRZ, Local Resource Zone, Planning, Demand, Loss of Load, Resource Adequacy
Describes LRZ purpose, how they are determined and details.
5706 view(s)
Jul 1, 2024
Keywords: Resource Adequacy, Planning Resources, Local Clearing Requirement, Local Resource Zone, LRZ, LSE, Planning Reserve Margin Requirement, PRMR
A sufficient volume of Planning Resources must be located in the same LRZ as the LSE's PRMR to meet the LRZ's LCR
278 view(s)
Jul 1, 2024
Keywords: DSRI, Demand Side Resource Interface, Monthly Availability, LMR, Load Modifying Resource, MWs Available for MISO, Self-Scheduled MWs, ZRC, Zonal Resource Credits, PRA, MECT, Module E, Resource Adequacy, Planning
Load Modifying Resource (LMR) Availability Data
1059 view(s)
Jun 3, 2024
Keywords: Planning Reserve Margin Requirement, PRMR, Zonal Resource Credit, Resource Adequacy, Planning
Each Load Serving Entity’s (LSE’s) total obligation will be referred to as the Planning Reserve Margin Requirement (PRMR).
3303 view(s)
Jul 1, 2024
Keywords: PRA, RA, Planning, Auction, LRZ, Load Reserve Zone
MISO’s PRA mechanics provide LSEs in MISO an option to procure Planning Resources through an annual auction process known as the Planning Resource Auction
2243 view(s)
Jul 1, 2024
Keywords: Utility, Commissioner, Regulatory, State, Regulator, RERRA, Resource Adequacy, Utilities, State, Electric, Retail, Authority
Describes the role and authority of state utility commissions and Relevant Electric Retail Regulatory Authorities (RERRA) in MISO’s Resource Adequacy.
582 view(s)
Jun 3, 2024
Keywords: Non-Coincident Peak, Submit, Load Forecast, Resource Adequacy, Planning, Summer, Winter, Seasonal
Market Participants serving load within MISO must submit a Non-Coincident Peak Load forecast(s) each year by midnight November 1st.
309 view(s)
Jun 3, 2024
Keywords: Submit, Energy, Load Forecast, Resource Adequacy, Planning Year, Peak Load, Seasonal, MECT, Module E
Market Participants serving load within MISO must submit an Energy For Load forecast(s) each year by midnight November 1.
371 view(s)
Jun 3, 2024
Keywords: Peak, Load Forecast, Submit, Resource Adequacy, Coincident Peak, Planning Year
Market Participants serving load within MISO must submit a Coincident Peak Load forecast(s) each year by midnight November 1
563 view(s)
Jul 1, 2024
Keywords: Zonal, Deliverability, ZDB, Resource Adequacy, Local Resource, LRZ, External Resource, ERZ, Sub-Regional, SRRZ, Planning, Auction
Price separation between Local Resource Zones (LRZs), External Resource Zones (ERZs), or groupings of LRZs, including Sub-Regional Resource Zone (SRRZs)
3271 view(s)
May 7, 2024
Keywords: MSE, Initiatives.
multi-year program is to transform our current platform into a flexible, upgradeable and secure system that will meet those needs.
153 view(s)
Dec 20, 2024
Keywords: Appendix H, MISO functional control, Transmission Facilities, above 100kV, transferred
Appendix H Transmission System Facilities is a listing of facilities a Transmission Owner has transferred to MISO for the purpose of planning and operation
909 view(s)
May 6, 2024
Keywords: Appendix G, Non-transferred Transmission Facilities, Agency Agreement, 100kV and below
Appendix G Agency Agreement is used for Non-Transferred Transmission Facilities which are transmission facilities that have not been transferred to MISO.
948 view(s)
May 6, 2024
Keywords: Resource Adequacy, PRA, Capacity, Market, ZRC, Zonal Resource Credit, Reserves, Energy, Contracts, Bilateral, Replacement
Accessing the Non-MISO Transaction Bulletin Board
788 view(s)
Dec 20, 2024
Keywords: Applications, Model-On-Demand, ShareFile, Access, MTEP, ShareFile, PROMOD, BAC, CSVLR, TOCTT, 881, MUG, OPSUG, RASUG, RCCTT, ROWG, WAMSUG, Flowgate, Generation Interconnection, Member Drills, Reliability Authority, Restricted, Access
Extranet, Citrix, Member Delivered Applications, Model-On-Demand, ShareFile, Access
15176 view(s)
Nov 18, 2024