The PRMR is calculated using the following equation, by Asset Owner, by Local Resource Zone (LRZ):
ππ
ππ
πΏπ
π= Ξ£ [(πΆππ·πβ πΉπ
π+πΉπ
π)Γ(1+ππΏ%) Γ(1+ππ
ππ
ππ)]
πΏπ΅π΄ Where:
PRMRLRZ = Planning Reserve Margin Requirement per LRZ
CPDf = Coincident Peak Demand forecast per LBA
FRP = Full Responsibility Purchase per LBA
FRS = Full Responsibility Sale per LBA
TL% = Transmission Loss Percentage of LBA
PRM RTO = Planning Reserve Margin in Unforced Capacity set by LOLE Studies
REFERENCE
BPM-011 Resource Adequacy